Update 14 November on the improvements works in Paddington Recreation Ground
The maintenance and improvement works keep progressing well. Here is the latest update for the following weeks.
- The works in the Environmental Area and Forest School are completed.
- The improvement works of the Playground Areas is completed.
- The Pavilion Changing Rooms work is completed.
- The Pathway Works have started and continue until further notice.
- The Bluebell Glade and the Forest Garden works have started and continue into the new year.
- The resurfacing of Tennis Courts 8 – 13 has started and is planned to finish this year.
- The maintenance and enabling works of Tennis Courts 1 – 7 will start on the 20th November and will finish on the 24th November.
* Please note that all dates are inclusive and weather dependant.
Please visit our dedicated page for Paddington Recreation Ground Improvements to find out the status of each of the works.