Update 1 August on the improvements works in Paddington Recreation Ground

The maintenance and improvement works keep progressing well. Here is the latest update for the following weeks.

  • The bark replenishment works along one section of the Environmental area is almost completed which includes the Forest and Wood Chip path.
  • The other path work on gravel and shrubs will start this week
  • Final planting will commence early next week.
  • The Pebble and Pond path is finished and planted up with new boulders and plants.
  • All fencing work has been completed.
  • The Pond works are likely to start in September. 

* Please note that all dates are inclusive and weather dependant.