Update 3 July on the improvements works in Paddington Recreation Ground
The maintenance and improvement works keep progressing well. Here is the latest update for the following weeks.
- Week commencing 3rd July
- Continuation of surfacing (all week)
- Forest Play will fully close from Monday 3rd July to Monday 10th July
- Pavilion Changing Rooms will have restricted access from Thursday 6th July to Thursday 20th July
- Infant side of the playground closed from Tuesday 4th July until Friday 21st July
- Week commencing 10th July
- Further work in the infant play area will be underway, but only the side of the ship will be closed from Monday 10th July to Wednesday 13th July
- Monday 10th July complete tree house area re open on the same day
- Tuesday 11th July start on infant area swing and roundabout
- Thursday 13th July base up train station section
- Week commencing 17th July
- Monday 17th July to Wednesday 19 July surfacing to install
- Thursday 20th July final work check and reopening of the area
* Please note that all dates are inclusive and weather dependant.